There are two projects, A and B (with the same risk involved), with a rate of return of 10 percent and X percent, respectively, if under normal circumstances, project B is selected. What could be the rate of return of Project B?
Answer & explanation
Correct answer: option 4
The correct answer is Option (4) → 12 percent
The rate of return is the most important point in choosing a project. When two projects carry the same risk, the one with the higher rate of return is selected. For example, if project A gives 10 per cent and project B gives 12 per cent, project B is chosen.
Here project B is selected. So its return must be more than project A’s 10 percent.
Option (1) 7 percent — Incorrect. 7 is less than 10, so project A would be chosen.
Option (2) 8 percent — Incorrect. 8 is less than 10, so project A would be chosen.
Option (3) 9 percent — Incorrect. 9 is less than 10, so project A would be chosen.
Option (4) 12 percent — Correct. 12 is more than 10. This is the only option that makes project B the better choice.
NCERT (2026-27 Edition): “The rate of return: The most important criterion is the rate of return of the project. These calculations are based on the expected returns from each proposal and the assessment of the risk involved. Suppose, there are two projects, A and B (with the same risk involved), with a rate of return of 10 per cent and 12 per cent, respectively, then under normal circumstance, project B should be selected.” |