Practicing Success

Target Exam

CUET

Subject

General Test

Chapter

Numerical Ability

Topic

Time and Work

Question:

A can do a piece of work alone in 96 days and B can do it alone in 104 days. In how many days can the duo, working together, complete the work?

Options:

49.94

49.92

49.96

49.88

Correct Answer:

49.92

Explanation:

A = 96 days,

B = 104 days,

⇒ Time required for A + B to complete the work = \(\frac{1248}{13+12}\) = \(\frac{1248}{25}\) = 49.92 days,  ..(\(\frac{Work}{Efficiency}\) = Time)