Read the passage and answer the following questions:
XYZ Logistics faced challenges in meeting delivery deadlines, leading to customer complaints. The management decided to implement a structured control process to ensure timely deliveries.
The company set a standard of delivering 95% of orders within the promised timeframe. A tracking system was introduced to monitor real-time delivery progress, ensuring accurate data collection. Monthly reports revealed that only 85% of orders were delivered on time, falling short of the 95% benchmark. Analysis showed delays occurred due to inefficient route planning and uncoordinated warehouse operations.
To address these issues, XYZ Logistics optimized route planning using AI-based software and trained warehouse staff to streamline operations.
After implementing changes, performance improved to 92% within the first month and met the 95% target in three months. Management regularly reviewed the system to maintain performance.
By implementing all elements of the controlling process, XYZ Logistics ensured continuous improvement and customer satisfaction.
What corrective action was taken for warehouse operations?
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → Employee training
Option (1) Hiring more staff — Incorrect. The company worked with its present staff. The passage does not mention any new hiring.
Option (2) Employee training — Correct. The passage says the company trained warehouse staff to streamline operations. A step taken to remove the cause of a deviation is corrective action, the last step of controlling. The warehouse problem was poor teamwork, so the staff were trained to work more smoothly. When a target is not met, corrective action might involve training of employees.
Option (3) Increasing storage capacity — Incorrect. Lack of space was not the problem. The passage names poor routes and poorly linked work.
Option (4) Outsourcing operations — Incorrect. The company did not give its warehouse work to an outside firm. It kept the work and improved it.
NCERT (2026-27 Edition): “Step 5: Taking Corrective Action: The final step in the controlling process is taking corrective action. No corrective action is required when the deviations are within acceptable limits. …” “Corrective action might involve training of employees if the production target could not be met. Similarly, if an important project is running behind schedule, corrective action might involve assigning of additional workers and equipment to the project and permission for overtime work. …” |