Arrange the following steps involved in controlling process in a proper sequence.
(A) Measuring actual performance by personal observation or performance report
(B) Analyze the deviation
(C) Setting performance standards
(D) Taking corrective action
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → (C), (A), (B), (D)
(C) Setting performance standards — this comes first. Standards are the targets against which work will be measured. Without them there is nothing to check the work against.
(A) Measuring actual performance by personal observation or performance report — this comes second. The manager finds out what has actually been done, for example by personal observation or performance reports.
(B) Analyze the deviation — this comes third. The actual work is compared with the standard. The gap between them, called the deviation, is studied to find its cause.
(D) Taking corrective action — this comes last. Once the cause is known, the manager acts to remove it, so that the work again meets the standard.
NCERT (2026-27 Edition): “Controlling Process Controlling is a systematic process involving the following steps. “Step 2: Measurement of Actual Performance: Once performance standards are set, the next step is measurement of actual performance. Performance should be measured in an objective and reliable manner. There are several techniques for measurement of performance. These include personal observation, sample checking, performance reports, etc. …” |