Question:

A car manufacturing plant produces Sedans and SUV's, using limited resources of steel, labour hours, and machine hours.

  • Each Sedan requires 6 tons of steel, 10 labour hours and 8 machine hours.
  • Each SUV requires 9 tons of steel, 15 labour hours and 12 machine hours.
  • Plant has 600 tons of steel, 1200 labour hours and 1000 machine hours.
  • Profit per Sedan is Rs. 50,000 and per SUV is Rs. 80,000

The optimal Profit is,

Options:

50,00,000

52,80,000

53,00,000

54,00,000

Correct Answer:

52,80,000

Explanation:

The correct answer is Option (4) → 52,80,000

Z optimal is at (0, 66).

$⇒Z(0,66)=50,000×0+80,000×66$

$=52,80,000$