Question:

A man complete a job in four days working ten hours a day. In how many days can he complete it if he works eight hours a day?

Options:

5

10

2.5

4

Correct Answer:

5

Explanation:

The total work is constant.

Total work done:

$4 \text{ days} \times 10 \text{ hours/day} = 40 \text{ hours}$

If he works 8 hours per day, the number of days required is:

$\frac{40}{8} = 5 \text{ days}$