Question:

A man complete a job in four days working ten hours a day. In how many days can he complete it if he works eight hours a day?

Options:

5

10

2.5

4

Correct Answer:

5

Explanation:

The formula that we used here is :-

M1 × D1 × H1 = M2 × D2 × H2

Where, M = Number of men

D = Number of days

H = Number of Hours taken

ATQ,

M1 × D1 × H1 = M2 × D2 × H2

1 × 4 × 10 = 1 × D2 × 8

40 = 8 × D2 

D2 = 5