Match List-I with List-II
|
List-I |
List-II |
|
(A) Setting Standards |
(I) The company has decided to increase the workforce to meet the shortage of production. |
|
(B) Measuring Actual Performance |
(II) Company sets target production rate of 1000 units per day |
|
(C) Taking Corrective Action |
(III) Acceptable deviations of actual performance from the standard performance is ± 50 units. |
|
(D) Analyzing Deviations |
(IV) The company produces 700 units per day. |
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → (A)-(II), (B)-(IV), (C)-(I), (D)-(III)
|
List-I |
List-II |
|
(A) Setting Standards |
(II) Company sets target production rate of 1000 units per day |
|
(B) Measuring Actual Performance |
(IV) The company produces 700 units per day. |
|
(C) Taking Corrective Action |
(I) The company has decided to increase the workforce to meet the shortage of production. |
|
(D) Analyzing Deviations |
(III) Acceptable deviations of actual performance from the standard performance is ± 50 units. |