Match List-I with List-II
| List-I | List-II |
| (A) Setting Standards | (I) The company has decided to increase the workforce to meet the shortage of production. |
| (B) Measuring Actual Performance | (II) Company sets target production rate of 1000 units per day |
| (C) Taking Corrective Action | (III) Acceptable deviations of actual performance from the standard performance are ± 50 units. |
| (D) Analyzing Deviations | (IV) The company produces 700 units per day. |
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → (A)-(II), (B)-(IV), (C)-(I), (D)-(III)
(A) Setting Standards — this matches (II) Company sets target production rate of 1000 units per day. A standard is the target against which work will be judged. 1000 units a day is that target.
(B) Measuring Actual Performance — this matches (IV) The company produces 700 units per day. This is the work actually done, found by measuring it.
(C) Taking Corrective Action — this matches (I) The company has decided to increase the workforce to meet the shortage of production. Output is 300 units short. Adding more workers is a step to correct this gap. A similar example is assigning additional workers to a project that is behind schedule.
(D) Analyzing Deviations — this matches (III) Acceptable deviations of actual performance from the standard performance are ± 50 units. In this step, the manager fixes the acceptable range of deviations. Only a gap bigger than 50 units needs attention. Here the gap is 300 units, so action is needed.
NCERT (2026-27 Edition): “Step 1: Setting Performance Standards: … The first step in the controlling process is setting up of performance standards. Standards are the criteria against which actual performance would be measured. Thus, standards serve as benchmarks towards which an organisation strives to work.” “Step 2: Measurement of Actual Performance: … Once performance standards are set, the next step is measurement of actual performance. Performance should be measured in an objective and reliable manner. There are several techniques for measurement of performance. These include personal observation, sample checking, performance reports, etc. …” “Step 4: Analysing Deviations: Some deviation in performance can be expected in all activities. It is, therefore, important to determine the acceptable range of deviations. …” “Step 5: Taking Corrective Action: The final step in the controlling process is taking corrective action. No corrective action is required when the deviations are within acceptable limits. However, when the deviations go beyond the acceptable range, especially in the important areas, it demands immediate managerial attention so that deviations do not occur again and standards are accomplished.” “Corrective action might involve training of employees if the production target could not be met. Similarly, if an important project is running behind schedule, corrective action might involve assigning of additional workers and equipment to the project and permission for overtime work. …” |