'He is responsible for timely and accurate completion of job'.
Identify the specialist as per one of Taylor's Technique of Scientific Management, stated above.
Answer & explanation
Correct answer: option 4
The correct answer is Option (4) → Speed Boss
Option (1) Gang Boss — Incorrect. He keeps machines and tools ready for operation by the workers.
Option (2) Time and Cost Clerk — Incorrect. He works under the planning in-charge and prepares the time and cost sheet.
Option (3) Inspector — Incorrect. He checks the quality of work.
Option (4) Speed Boss — Correct. The speed boss is one of the four specialists under the production in-charge. He is responsible for timely and accurate completion of the job.
NCERT (2026-27 Edition): “Functional Foremanship … Under Production incharge, personnel who would work were speed boss, gang boss, repair boss, and inspector. These respectively were responsible for timely and accurate completion of job, keeping machines and tools etc., ready for operation by workers, ensure proper working condition of machines and tools and check the quality of work.” “…Under planning incharge four personnel namely instruction card clerk, route clerk, time and cost clerk and a disciplinarian worked. These four personnel would draft instructions for the workers, specify the route of production, prepare time and cost sheet and ensure discipline respectively.” |