A can do a piece of work in 24 days and B in 40 days. They work together for 12 days and then both leave the work. Then C alone finishes the remaining work in 6 days. In how many days will C finish the full work? |
30 days 36 days 39 days 25 days |
30 days |
A : B Days 24 : 40 = 3 : 5 Efficiency 5 : 3 Say, the total work = 120 Work done A + B in 8 days = Efficiency x No. Of Days = (3 + 5) x 12 = 8 x 12 = 96 Remaining work = 120 - 96 = 24 This work is completed by C in 6 days, Thus efficiency of C = \(\frac{Work}{Days}\) = \(\frac{24}{6}\) = 4 Time taken By C alone to complete this work = \(\frac{Total\; work}{Efficiency}\) = \(\frac{120}{4}\) = 30 days |