If 20 men can complete a piece of work in 18 days working 5 hours per day, in how many days can 25 men complete it, working 6 hours per day? |
10 days 13 days 11 days 12 days |
12 days |
Formula to be used here, \( { M}_{1 } \) x \( { D}_{1 } \) x \( { H}_{1 } \) = \( { M}_{2 } \) x \( { D}_{2 } \) x \( { H}_{2 } \) where, M = No. of Men, D = No. of Days, H = No. of Hours, ⇒ 20 x 18 x 5 = 25 x \( { D}_{2 } \) x 6 ⇒ \( { D}_{2 } \) = 12 days, |