P and Q can complete a job in 24 days working together. P can alone complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining job is: |
26 days 30 days 64 days 60 days |
64 days |
The correct answer is Option (3) → 64 days Work done by P and Q together in 1 day = 1⁄24 Work done by P alone in 1 day = 1⁄32 Work done by Q alone in 1 day = 1⁄24 − 1⁄32 Work done by P and Q in 8 days = 8 × 1⁄24 Remaining work = 1 − 1⁄3 Time taken by Q to complete remaining work = (2⁄3) ÷ (1⁄96) |