"In company Ace Ltd, if the plans lay down a 2 percent increase in labor cost as an acceptable range of deviation, only an increase in labor cost beyond 2 percent should be brought to the notice of the management. However, in case of major deviation from the standard (say, 5 percent), the matter has to receive immediate action from management on a priority basis".
Identify the concept of management highlighted in the aforesaid statement.
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → Management by exception
Option (1) Management by exception — Correct. Management by exception (control by exception) is based on the belief that trying to control everything ends in controlling nothing. So only significant deviations that go beyond the permissible limit are brought to the notice of management. In the case, a rise in labour cost up to 2% is allowed. Only a rise above 2% is reported, and a 5% rise needs immediate action.
Option (2) Critical point control — Incorrect. Critical point control means focusing control on the key result areas that are critical to the firm’s success. It tells the manager which areas to watch. The case is about how big a deviation must be before it is reported.
Option (3) Exception by analysis — Incorrect. There is no such term.
Option (4) Critical plan control — Incorrect. There is no such term.
NCERT (2026-27 Edition): “Critical Point Control: It is neither economical nor easy to keep a check on each and every activity in an organisation. Control should, therefore, focus on key result areas (KRAs) which are critical to the success of an organisation. These KRAs are set as the critical points. …” “Management by Exception: Management by exception, which is often referred to as control by exception, is an important principle of management control based on the belief that an attempt to control everything results in controlling nothing. Thus, only significant deviations which go beyond the permissible limit should be brought to the notice of management. Thus, if the plans lay down 2 per cent increase in labour cost as an acceptable range of deviation in a manufacturing organisation, only increase in labour cost beyond 2 per cent should be brought to the notice of the management. However, in case of major deviation from the standard (say, 5 per cent), the matter has to receive immediate action of management on a priority basis.” |