Identify the correct sequence of the Planning Process:
A. Developing premises
B. Selecting an alternative
C. Implementing the plan
D. Setting objectives
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → D, A, B, C
(D) Setting objectives — First. Planning begins by deciding what the organisation wants to achieve. Every later step works towards these objectives.
(A) Developing premises — Second. Plans are made for the future, so the manager must make assumptions about the future. These assumptions are the premises on which the plan rests.
(B) Selecting an alternative — Third. The manager identifies and evaluates the different ways of reaching the objectives, and then selects the best one. This can be done only after the objectives and premises are known.
(C) Implementing the plan — Fourth. The chosen plan is put into action. A plan cannot be put into action before it is chosen.
NCERT (2026-27 Edition): “Planning Process … (i) Setting Objectives: The first and foremost step is setting objectives. Every organisation must have certain objectives. …” “(ii) Developing Premises: Planning is concerned with the future which is uncertain and every planner is using conjecture about what might happen in future.” “(v) Selecting an alternative: This is the real point of decision making. The best plan has to be adopted and implemented. …” “(vi) Implementing the plan: This is the step where other managerial functions also come into the picture. The step is concerned with putting the plan into action, i.e., doing what is required. …” |