Match List-I with List-II.
| List-I (Situation) | List-II (Corrective action) |
|---|---|
| (A) Production target could not be met because workers lack the required skill | (I) No corrective action is required |
| (B) An important project is running behind schedule | (II) Training of employees |
| (C) The deviation cannot be corrected through managerial action | (III) Revision of the standards |
| (D) The deviations are within acceptable limits | (IV) Assigning additional workers and equipment, and permission for overtime work |
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → (A)-(II), (B)-(IV), (C)-(III), (D)-(I)
| List-I | List-II | Reason |
|---|---|---|
| (A) Production target could not be met because workers lack the required skill | (II) Training of employees | Workers who lack the required skill cannot meet the production target, so the cause is removed by training of employees. |
| (B) An important project is running behind schedule | (IV) Assigning additional workers and equipment, and permission for overtime work | A project running behind schedule needs more hands and more time, so it is speeded up by assigning of additional workers and equipment and permission for overtime work. |
| (C) The deviation cannot be corrected through managerial action | (III) Revision of the standards | Managerial action cannot remove this deviation, so the remedy left is to change the target itself: the standards may have to be revised. |
| (D) The deviations are within acceptable limits | (I) No corrective action is required | The deviation here stays within acceptable limits, so it needs no remedy and no corrective action is required. |
NCERT Extract (2026-27 Edition): Step 5: Taking Corrective Action: “Corrective action might involve training of employees if the production target could not be met. Similarly, if an important project is running behind schedule, corrective action might involve assigning of additional workers and equipment to the project and permission for overtime work. In case the deviation cannot be corrected through managerial action, the standards may have to be revised.” “No corrective action is required when the deviations are within acceptable limits.” |