A and B can complete a work in 20 days and 30 days respectively. A works full time but B works half time. In how many days the entire work is to be completed? |
9 days 15 days 12 days 10 days |
15 days |
A = 20 days, B = 30 days, ⇒ As B works half time, therefore his efficiency will be taken as half of original i.e; Half of 2 = 1, ⇒ Time required by A + B to complete the work = \(\frac{60}{3+1}\) = \(\frac{60}{4}\) = 15 days. ..(\(\frac{Work}{Efficiency}\) = Time) |