X men can finish a piece of work in 50 days. If there were 8 men more, the work could be finished in 10 days less. The original number of men is: |
7 10 12 32 |
32 |
(Total work = No. of men × no. of days) ATQ, X × 50 = (X+8) × 40 X × 50 = (X × 40) + (8 × 40) 50X - 40X = 320 10X = 320 X = 32 |