A, B and C together can do a piece of work in 6 days. A and B together can do the same work in 12 days. B alone can do the same work in 18 days. In how many days can A and C together do the same work? |
9 days 10.5 days 8 days 7.5 days |
9 days |
A + B + C = 6 days, A + B = 12 days, B = 18 days, ⇒ A + B + C = 6 (Efficiency) ⇒ A + C + 2 = 6, ⇒ A + C = 4, ⇒ Time required by A + C to complete the work = \(\frac{36}{4}\) = 9 days, ..(\(\frac{Work}{Efficiency}\) = Time) |