Practicing Success

Target Exam

CUET

Subject

Business Studies

Chapter

Controlling

Question:

The controlling technique 'PERT' stands for -

Options:

Programming Editing and Review Technique

Programme Evaluation and Review Technique

Programme Evaluations and Recognition Technique

Provision of Evaluation and Recognition Technique

Correct Answer:

Programme Evaluation and Review Technique

Explanation:

The correct answer is option (2) : Programme Evaluation and Review Technique

PERT (Programme Evaluation and Review Technique) important network techniques useful in planning and controlling. These techniques are especially useful for planning, scheduling and implementing time bound projects involving performance of a variety of complex, diverse and interrelated activities. These techniques deals with time scheduling and resource allocation for these activities and aims at effective execution of projects within given time schedule and structure of costs.