Abhimanyu can do 25% of a piece of work in 5 days. How many days will he take to complete the work ten times?
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → 200 days
Working at a steady rate, the time taken grows in proportion to the work done. So the time for the whole work is found first.
25% of the work, that is one-fourth, takes 5 days, so the whole work takes \(4\times5=20\) days
Ten times the work takes \(10\times20=200\) days