Match List I with List II.
| List I | List II |
| (A) Strategy | (I) Prescribed way of doing a task |
| (B) Method | (II) Detailed statements about a project |
| (C) Programme | (III) Exact manner in which a particular activity is to be done |
| (D) Procedure | (IV) Comprehensive plan for accomplishing objectives |
Choose the correct answer from the options given below :
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → A-IV, B-I, C-II, D-III
(A) Strategy — this matches (IV) Comprehensive plan for accomplishing objectives. A strategy gives the overall direction of the business. It covers the long-term goals, the course of action and the resources needed.
(B) Method — this matches (I) Prescribed way of doing a task. A method tells how one task, often one step of a procedure, is to be done.
(C) Programme — this matches (II) Detailed statements about a project. A programme gives the details of a project: its goals, policies, procedures, rules, tasks, resources and budget.
(D) Procedure — this matches (III) Exact manner in which a particular activity is to be done. A procedure is a set of routine steps, in a fixed order, for doing an activity.
NCERT (2026-27 Edition): “Strategy A strategy provides the broad contours of an organisation’s business. It will also refer to future decisions defining the organisations direction and scope in the long run. Thus, we can say a strategy is a comprehensive plan for accomplishing an organisation objectives. …” “Procedure Procedures are routine steps on how to carry out activities. They detail the exact manner in which any work is to be performed. They are specified in a chronological order. …” “Method Methods provide the prescribed ways or manner in which a task has to be performed considering the objective. It deals with a task comprising one step of a procedure and specifies how this step is to be performed. …” “Programme Programmes are detailed statements about a project which outlines the objectives, policies, procedures, rules, tasks, human and physical resources required and the budget to implement any course of action. …” |