A and B can finish a piece of work in 12 days and 15 days respectively. Together they start the work but after few days B left the job and A finished the remaining work in 3 days. If A and B get total Rs.6600 for the job, then find B’s share. |
2000 2200 2500 3300 |
2200 |
Total work = Efficiency × Number of days work done by A in last 3 days when B left the work = 5R ×3 = 15R remaining work = 60R - 15R = 45R Time taken = \(\frac{45R}{9R}\) = 5 days total work by A = 5R × 5 + 15R = 40R total work by B = 20R ratio of their work A : B 2 : 1 the ratio in which amount is paid is same as ratio of their work 3R = 6600 1R = 2200 is the share of B |