A and B can do a piece of work in 20 days and 25 days respectively . Efficiency of C is 25% more than the efficiency of B . find the tome taken by C to do the complete work . |
14 20 16 18 |
20 |
Efficiency of C is 25% more than the efficiency of B i.e. ratio of B : C 4 : 5 as 4R = 4 so, 5r = 5 Efficiency × Days = Total work time taken by C to complete the work = \(\frac{100}{5}\) = 20 days |