14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work? |
10 14 12 15 |
10 |
Using formula, \( { M}_{1 } \) x \( { D}_{1 } \) = \( { M}_{2 } \) x \( { D}_{2} \) where, M = no. of men, D = no. of days ⇒ 14 x 15 = 21 x \( { D}_{2} \) ⇒ \( { D}_{2} \) = 10 days. Therefore 21 men will complete the work in 10 days. |