A takes 8 more days than B to finish a work. A and B start the work and B leaves the work 9 days before the completion of the work. If A completes 75% of the work. How long would A have taken to finish the work alone? |
20 14 15 16 |
14 |
Let the time taken by B working alone = x days so, time taken by A working alone = (x + 8) days A completes 75% of work, so the day he will work = 75% of (x + 8) = \(\frac{3(x + 8)}{4}\) ⇒ B has to complete 25% of work, hence, days taken by B = 25% of x = \(\frac{x}{4}\) B leaves the work 9 days before the work is finished hence, days for which A worked - days for which B worked = 9 days \(\frac{3(x + 8)}{4}\) - \(\frac{x}{4}\) = 9 \(\frac{3x + 24 - x}{4}\) = 9 2x = 12 x = 6 Time taken by A to finish the work = x + 8 = 6 + 8 = 14 days |