A can do a piece of work in 16 days and B completes the same in 36 days. Both complete the work together and earn ₨. 728, then find B's share?
Answer & explanation
Correct answer: option 2
A : B
Days 16 : 36 = 4 : 9
Efficiency 9 : 4
B's share = \(\frac{4}{13}\) x 728 = ₨. 224