A work can be completed by 8 boys in 48 days. If 2 boys leave after working for 24 days, then how many days will be needed to complete the remaining work? |
20 days 24 days 32 days 30 days |
32 days |
Formula to be used : ⇒ \( { M}_{1 } \) x \( { D}_{1 } \) = \( { M}_{2 } \) x \( { D}_{2 } \) where, M = N. of men, D = No. of days, ⇒ Putting values in the formula; ⇒ 8 x 24 = 6 x \( { D}_{2 } \) ⇒ \( { D}_{2 } \) = 32 days. |