If A had worked alone, he would have taken 60 days to complete a work. If he is joined by B, they complete the same work in 48 days and get paid ₨ 1750. What is B's share? |
Rs 496 Rs 450 Rs 350 Rs 368 |
Rs 350 |
A : A + B Days 60 : 48 Efficiency 4 : 5 Eff. of B = 5 - 4 = 1 B's share = \(\frac{1}{5}\) x 1750 = Rs 350 |