Arrange the following steps of controlling in proper order.
(a) Analysing deviation
(b) Comparing actual performance with standards
(c) Setting performance standards
(d) Taking corrective action
(e) Measurement of actual performance
Choose the most appropriate answer from the options given below :
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → (c), (e), (b), (a), (d)
Step 1 – (c) Setting performance standards — First we must decide the targets (standards) against which work will be judged.
Step 2 – (e) Measurement of actual performance — Next the actual work done is measured.
Step 3 – (b) Comparing actual performance with standards — The measured result is compared with the standard to find the difference.
Step 4 – (a) Analysing deviation — The causes of the difference (deviation) are studied.
Step 5 – (d) Taking corrective action — The last step is to correct the problem found.
NCERT (2026-27 Edition): “Step 1: Setting Performance Standards: … The first step in the controlling process is setting up of performance standards. Standards are the criteria against which actual performance would be measured. Thus, standards serve as benchmarks towards which an organisation strives to work.” “Step 2: Measurement of Actual Performance: … Once performance standards are set, the next step is measurement of actual performance. Performance should be measured in an objective and reliable manner. There are several techniques for measurement of performance. These include personal observation, sample checking, performance reports, etc. As far as possible, performance should be measured in the same units in which standards are set as this would make their comparison easier.” “Step 3: Comparing Actual Performance with Standards: … This step involves comparison of actual performance with the standard. Such comparison will reveal the deviation between actual and desired results. Comparison becomes easier when standards are set in quantitative terms. For instance, performance of a worker in terms of units produced in a week can be easily measured against the standard output for the week.” “Step 4: Analysing Deviations: … After identifying the deviations that demand managerial attention, these deviations need to be analysed for their causes. Deviations may have multiple causes for their origin. …” “Step 5: Taking Corrective Action: The final step in the controlling process is taking corrective action. No corrective action is required when the deviations are within acceptable limits. …” |