C can do a work alone in 120 days. B is twice as efficient as C and A is thrice as efficient as B. In how many days can they together complete the work? |
13.33 16.67 12.5 15 |
13.33 |
C = 120 days, According to the question, A : B : C ⇒ 3 : 1 ⇒ : 2 : 1 ⇒ 6 : 2 : 1 (Efficiency) ⇒ Total work = 1 x 120 days = 120 units, ..(Efficiency × Days = Total work)
⇒ Time required by A + B + C to complete the total work = \(\frac{120}{6+2+1}\) = \(\frac{120}{9}\) = 13.33 days ..(\(\frac{Work}{Efficiency}\) = Time) |