A can do $\frac{1}{4}^{\text {th}}$ of a work in 3 days and B can do $\frac{1}{6}^{\text {th}}$ of the same work in 4 days. How much will A get if both worked together and are paid ₹18,000 in all? |
₹13,000 ₹10,000 ₹14,000 ₹12,000 |
₹12,000 |
A can do $\frac{1}{4}^{\text {th}}$ of a work = 3 days A can do complete work in = 4 × 3 = 12 days B can do $\frac{1}{6}^{\text {th}}$ of a work = 4 days B can do complete work in = 6 × 4 = 24 days Total work = efficiency × time A : B Time 12 : 24 1 : 2 Efficiency 2 : 1 Profit ratio divide according to efficiency ratio. 3R = 18000 1R = 6000 So, share of A = 2R = 2 × 6000 = 12000 The correct answer is Option (1) → ₹12,000 |