Which of the following statements about a budget is NOT correct?
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → A budget is a standing plan used for activities that occur regularly.
Option (1) A budget is a statement of expected results expressed in numerical terms. — True. A budget puts the expected results in numbers.
Option (2) A budget is also a control device from which deviations can be taken care of. — True. Actual figures are compared with expected figures, so deviations can be corrected.
Option (3) A budget is a standing plan used for activities that occur regularly. — False. A budget is a single-use plan, made for a specified period. Policies, procedures, methods and rules are the standing plans.
Option (4) Making a budget involves forecasting. — True. A budget rests on forecasting, so it comes under planning.
NCERT (2026-27 Edition): “Single-use Plan: A single-use plan is developed for a one-time event or project. Such a course of action is not likely to be repeated in future, i.e., they are for non-recurring situations. The duration of this plan may depend upon the type of the project. It may span a week or a month. A project may sometimes be of only one day, such as, organising an event or a seminar or conference. These plans include budgets, programmes and projects. …” “Budget A budget is a statement of expected results expressed in numerical terms. It is a plan which quantifies future facts and figures. For example, a sales budget may forecast the sales of different products in each area for a particular month. A budget may also be prepared to show the number of workers required in the factory at peak production times. Since budget represents all items in numbers, it becomes easier to compare actual figures with expected figures and take corrective action subsequently. Thus, a budget is also a control device from which deviations can be taken care of. But making a budget involves forecasting, therefore, it clearly comes under planning. It is a fundamental planning instrument in many organisations. …” |