A can do $\frac{2}{5}$ of a work in 12 days while B can do $66\frac{2}{3}\%$ of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in: |
6 days 8 days 4 days 9 days |
6 days |
A = \(\frac{2}{5}\)W = 12 days = 30 days, B = \(\frac{2}{3}\)W = 16 days = 24 days, ⇒ A + B worked for 10 days = (4 + 5) x 10 = 90 units ..(Efficiency × Days = Total work) ⇒ Remaining work = 120 - 90 = 30 units. ⇒ Time required by B to complete 30 units of work = \(\frac{30}{5}\) = 6 days. ..(\(\frac{Work}{Efficiency}\) = Time) |