Identify the correct sequence of controlling process in management:
(A) Deviation analysis
(B) Setting standards
(C) Comparison of actual performance with standards
(D) Performance measurement
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → (B), (D), (C), (A)
(B) Setting standards — the first step. Standards are the targets against which actual work will be judged.
(D) Performance measurement — next, the actual performance is measured, as far as possible in the same units as the standards.
(C) Comparison of actual performance with standards — the measured performance is then compared with the standard. This comparison shows the deviation, that is, the gap between actual and desired results.
(A) Deviation analysis — the deviations are then studied to find their causes. Only the important ones are brought to the manager. Corrective action, the last step of controlling, comes after this.
NCERT (2026-27 Edition): “Controlling Process Controlling is a systematic process involving the following steps. |