‘Finally after an arduous quest and several tests of soil and fridge designs, he emerged with the innovative Mitticool fridge in 2005.’
Testing several soils and fridge designs before settling on the final fridge is closest to which step of the planning process?
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → Evaluating alternative courses
| Option | Reason |
|---|---|
| Option (1) Developing premises. Incorrect. | Developing premises means making assumptions about the uncertain future; testing soils and fridge designs is not a guess about the future but a check of real choices, so it is not this step. |
| Option (2) Evaluating alternative courses. Correct. | Evaluating alternative courses means weighing the pros and cons of each alternative; each soil and design was an alternative tested before the final fridge was chosen, so this is the step. |
| Option (3) Follow-up action. Incorrect. | Follow-up action monitors a plan already put into action; here the final design was still being chosen, so there was no running plan to monitor. |
| Option (4) Setting objectives. Incorrect. | Setting objectives states what the organisation wants to achieve; the tests state no goal but compare ways of making the fridge, so this is not the step. |
NCERT Extract (2026-27 Edition): Correct option (2) Kinds of plans: Objective, Strategy and Policy of Mitticool: “Finally after an arduous quest and several tests of soil and fridge designs, he emerged with the innovative Mitticool fridge in 2005.” (iv) Evaluating alternative courses: “The next step is to weigh the pros and cons of each alternative. … The positive and negative aspects of each proposal need to be evaluated in the light of the objective to be achieved. … Alternatives are evaluated in the light of their feasibility and consequences.” Wrong options (1), (3) and (4) (i) Setting Objectives: “Objectives or goals specify what the organisation wants to achieve.” (ii) Developing Premises: “Planning is concerned with the future which is uncertain and every planner is using conjecture about what might happen in future.” |