Controlling

Question:

When are deviations said to be positive in nature?

Options:

Planned performance is more than the actual performance

Actual performance is more than the planned performance

Both planned and actual performances are same

None of the above

Correct Answer:

Actual performance is more than the planned performance

Explanation:

The correct answer is option 2- Actual performance is more than the planned performance.

Deviations are said to be positive when actual performance is more than planned performance.

Deviations are said to be positive in nature when the actual performance is more than the planned performance. This indicates that the results exceeded expectations. So the correct option is Actual performance is more than the planned performance.