Question:

Since the future cannot be predicted with absolute accuracy, ______ premises may not be fully reliable.

Options:

Delegating

Planning

Coordination

Controlling

Correct Answer:

Planning

Explanation:

The correct answer is Option (2) → Planning

Planning is based on certain assumptions or premises about future conditions. Since the future is uncertain and cannot be predicted with complete accuracy, planning premises may not always be fully reliable, which can affect the success of the plan.