Identify the responsibility of "Gang Boss" in functional foremanship.
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → Keeping tools and machine ready
Option (1) Ensure proper working conditions of machine and tools — Incorrect. This is the job of the repair boss.
Option (2) Keeping tools and machine ready — Correct. This is the job of the gang boss, one of the four bosses under the production incharge. He is responsible for keeping machines and tools ready for operation by workers.
Option (3) Specify the path of production — Incorrect. This is the job of the route clerk, who works under the planning incharge.
Option (4) Maintaining required speed of production — Incorrect. This is the job of the speed boss, who sees that the work is finished on time.
NCERT (2026-27 Edition): “Functional Foremanship … Taylor advocated separation of planning and execution functions. This concept was extended to the lowest level of the shop floor. It was known as functional foremanship. Under the factory manager there was a planning incharge and a production incharge. Under planning incharge four personnel namely instruction card clerk, route clerk, time and cost clerk and a disciplinarian worked. These four personnel would draft instructions for the workers, specify the route of production, prepare time and cost sheet and ensure discipline respectively.” “Under Production incharge, personnel who would work were speed boss, gang boss, repair boss, and inspector. These respectively were responsible for timely and accurate completion of job, keeping machines and tools etc., ready for operation by workers, ensure proper working condition of machines and tools and check the quality of work.” |