Practicing Success
Working together A and B can complete a work in 12 days. They work together for 9 days after which B leaves. If A finishes the remaining work in 5 days, then the number of days that B alone would take to complete the work is: |
12 24 30 15 |
30 |
A + B = 12 days, Let efficiency pf A + B be 2, Therefore, total work = 2 x 12 = 24 units, ..(Efficiency × Days = Total work) ⇒ A + B worked for 9 days = 2 x 9 = 18 units, ⇒ Remaining work = 24 - 18 = 6 units, ⇒ B left, so A completed the remaining work in 5 days = \(\frac{6}{A}\) = 5 days, ⇒ A = \(\frac{6}{5}\) (Efficiency)
⇒ So B = 2 - \(\frac{6}{5}\) = (\frac{4}{5}\), Therefore, time taken by B to complete the total work = \(\frac{24}{4/5}\) = 30 days, ..(\(\frac{Work}{Efficiency}\) = Time) |