A and B can complete a work in 36 days and 45 days respectively. They worked together for 2 days and then A left the work. In how many days will B complete the remaining work? |
41.5 40 41 40.5 |
40.5 |
A = 36 days, B = 45 days, ⇒ Before A left, they both worked for 2 days = (5 + 4) x 2 = 18 units ⇒ Remaining work = 180 - 18 = 162 units. ⇒ Time taken by B to complete remaining work = \(\frac{162}{4}\) = 40.5 days. |