Select the correct sequence of steps of controlling process which are given below.
A. Analysing deviations
B. Measurement of actual performance
C. Setting performance standards
D. Comparison of actual performance with standards
E. Taking corrective action
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → C, B, D, A, E
C. Setting performance standards — first. Standards are the targets against which actual work is measured.
B. Measurement of actual performance — second. The actual work done is measured.
D. Comparison of actual performance with standards — third. The measured work is compared with the standards.
A. Analysing deviations — fourth. The gap between actual and standard is studied and its causes are found.
E. Taking corrective action — last. This is the final step. It removes the causes of the deviation.
NCERT (2026-27 Edition): “Controlling Process Controlling is a systematic process involving the following steps. 1. Setting performance standards 2. Measurement of actual performance 3. Comparison of actual performance with standards 4. Analysing deviations 5. Taking corrective action” “Summary … The process of control involves setting performance standards, measurement of actual performance, comparison of actual performance with standards, analysis of deviations and taking corrective action.” |