A work that could be completed in 10 days was completed in 8 days as 5 more men joined at the start of work. What was the total number of men before the 5 men joined? |
18 10 20 12 |
20 |
Formula to be used here, \( { M}_{1 } \) x \( { D}_{1 } \) = \( { M}_{2 } \) x \( { D}_{2 } \) where, M = No. of Men, D = No. of Days, ⇒ Putting values in the formula, ⇒ M x 10 = (M + 5) x 8 ⇒ 5M = 20 + 4M ⇒ M = 20. |