Working 12 hours per day, Raj can complete a work in 12 days. How many hours per day should he work so as to finish the same work in 9 days? |
20 hours 24 hours 12 hours 16 hours |
16 hours |
The formula for work is $\frac{M \times H \times D}{Work}$ = Constant M = no. of men, H = hourse worked per day, D = no. of days Thus, for the same man doing the same job, Hours x Days = constant Then, to complete the work in 9 days, 12 x 12 = Hours x 9 Hours = 16 |