P and Q together can complete a work in 20 days. If Q alone can complete the work in 25 days, then in how many days P alone can complete the same work ?
Answer & explanation
Correct answer: option 2

Time taken by P alone to complete the work = $\frac{total\; work}{efficiency}$ = $\frac{100}{1}$
= 100 days