Arrange the following steps of Planning Process in a correct sequence.
(A) Evaluation of alternatives
(B) Search for alternative
(C) Determining Planning premises
(D) Selection of an alternative
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → (C), (B), (A), (D)
-
(C) Determining Planning Premises. First step is to identify assumptions and conditions (like resources, policies, environment) under which planning will be carried out.
-
(B) Search for Alternatives. Different possible courses of action are identified to achieve objectives.
-
(A) Evaluation of Alternatives. Each alternative is analyzed in terms of costs, benefits, feasibility, and risks.
-
(D) Selection of an Alternative. The best and most feasible alternative is chosen.