Identify the correct sequence of first five steps of controlling process.
A. Comparing actual performance with standards
B. Setting performance standards
C. Measurement of actual performance
D. Analysing deviations
E. Taking corrective action
Choose the correct answer from the options given below :
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → B, C, A, D, E
(B) Setting performance standards — step 1. The manager first fixes the targets (standards) against which work will be judged.
(C) Measurement of actual performance — step 2. The work actually done is measured, for example by personal observation or performance reports.
(A) Comparing actual performance with standards — step 3. The actual result is compared with the target. This shows the deviation (the gap).
(D) Analysing deviations — step 4. The causes of the gap are found.
(E) Taking corrective action — step 5, the final step. Action is taken to remove the cause of the gap.
NCERT (2026-27 Edition): “Step 1: Setting Performance Standards: … The first step in the controlling process is setting up of performance standards. …” “Step 2: Measurement of Actual Performance: … Once performance standards are set, the next step is measurement of actual performance. …” “Step 3: Comparing Actual Performance with Standards: … This step involves comparison of actual performance with the standard. Such comparison will reveal the deviation between actual and desired results. …” “Step 4: Analysing Deviations: … After identifying the deviations that demand managerial attention, these deviations need to be analysed for their causes. …” “Step 5: Taking Corrective Action: The final step in the controlling process is taking corrective action. …” |