S alone can do a piece of work in 14 days. T alone can do the same work in 21 days. U alone can do the same work in 28 days. Working together, in how many days will they complete the work? |
$\frac{84}{13}$ days $\frac{77}{13}$ days $\frac{71}{13}$ days $\frac{87}{13}$ days |
$\frac{84}{13}$ days |
S = 14 days, T = 21 days, U = 28 days, ⇒ Time required by S + T + U to complete the work = \(\frac{84}{13}\) days. ..(\(\frac{Work}{Efficiency}\) = Time) |