Eight people can complete a piece of work in 14 days. How many additional people will be required to complete triple of the work in 8 days? |
28 34 42 14 |
34 |
Total Work Done = Number of Days × Efficiency. To do the triple work in 8 days the total men required = 3 × 112/8 = 42 Extra men = 42 – 8 = 34 |