A and B can do a work in 12 days, B and C in 15 days and A, B and C together take 10 days. Find the number of days taken by B alone. |
20 24 60 90 |
20 |
Adding the efficiencies, (A + B) + (B + C) = 9 (A + B + C) + B = 9 6 + B = 9 B = 3 Time taken by B alone = \(\frac{Total \; Work}{Efficiency}\) = \(\frac{60}{3}\) = 20 days |