A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is: |
128 days 64 days 32 days 16 days |
64 days |
The correct answer is Option (2) → 64 days 1. Calculate the Work Capacity of A and B
2. Find B's 1-Day Work Capacity To find how much work B does in a single day, subtract A's capacity from their combined capacity: $\text{B's 1-day work} = \frac{1}{24} - \frac{1}{32}$ Finding the least common multiple (LCM) of 24 and 32 (which is 96): $\text{B's 1-day work} = \frac{4}{96} - \frac{3}{96} = \frac{1}{96}$ This means B alone would take 96 days to complete the entire job. 3. Calculate the Work Done and Remaining Work
4. Calculate the Time Taken by B for the Remaining Work Now, we find how long it takes B to complete the remaining $\frac{2}{3}$ of the job: $\text{Days} = \frac{\text{Remaining Work}}{\text{B's 1-day work}}$ $\text{Days} = \frac{2/3}{1/96}$ $\text{Days} = \frac{2}{3} \times 96 = 2 \times 32 = \mathbf{64 \text{ days}}$ |