Read the following passage and answer the question. XYZ Ltd. is a large company engaged in assembly of room-heaters. Recently the company had conducted the various studies and concluded that on an average a worker can assemble 25 room heaters in a day. The target volume of the company in a day is assembling of 2,500 units of room-heaters. However, the assembly of room heaters per day is 2,000 units only. To find out the reason, the company compared actual performance of each worker and observed that some of the workers were busy in gossiping. The company decided to keep a close check on the activities of the workers to minimise the dishonest and unethical behaviour as the part of workers. |
"To find out the reason, the company compared actual performance of each worker and observed that some of the workers were busy in gossiping." Identify the step in the controlling process highlighted in the given lines. |
Measurement of Actual Performance Comparing Actual Performance with Standards Analysing Deviations Taking Corrective Actions |
Analysing Deviations |
The correct answer is option 3- Analysing Deviations. The step in the controlling process highlighted in the given lines is Analyzing Deviations. |